When Will the A9 Be Fully Dualled Between Perth and Inverness?

The A9 between Perth and Inverness is due to be fully dualled by the end of 2035. This is the official target set by Transport Scotland. The date first appeared in the Delivery Plan of December 2023. The Government confirmed it again in January 2026 and added new funding and procurement details.

Treat that date as a plan commitment rather than a settled fact. The completion date has already been moved once. The remaining sections still depend on procurement, contract award and construction going as planned.

Scroll down

This guide covers how the target has changed and the milestones leading up to 2035. It also looks at which parts of the route are open and how the remaining work is funded and contracted. Finally, it sets out the latest official progress update and the uncertainty that remains.

The Official Completion Date

According to the responsible authority, the answer is the end of 2035.

Transport Scotland’s A9 dualling programme pages state that the Government set out a Delivery Plan in December 2023. Its aim was to complete A9 dualling by the end of 2035. The A9 Dualling Delivery Plan Update of 14 January 2026 restated that target. It says the Scottish Government is fully committed to delivering A9 dualling by the end of 2035.

This is the official planned completion date. It is not a guaranteed outcome. The sections below explain why that difference matters.

The Target Date Has Moved Before

Many readers will remember an earlier completion date. That memory is correct.

In December 2011, Scottish Ministers committed to dualling the A9 between Perth and Inverness by 2025. The Government replaced that commitment in December 2023. Its new Delivery Plan set the target completion at the end of 2035.

A9 dualling target moved from 2025 to the end of 2035 in the December 2023 Delivery Plan

This is the most useful context for judging how much weight to give the current date. Coverage of the A9 dualling programme written before December 2023 will usually refer to 2025. Anything written since will refer to 2035. The completion date has a documented record of moving. Keep this in mind when reading any future schedule for the upgrade.

Milestones on the Way to 2035

Full dualling will not happen all at once in 2035. The programme covers 83 miles (133km) of single carriageway between Perth and Inverness. The work is split into 10 separate sections. Each section is due to open as it is completed.

Transport Scotland has published milestones for the whole corridor. They show how much of the route should be dual carriageway at four points:

  • End of 2030: 50% of the route dualled
  • End of 2032: 67% dualled
  • End of 2034: 91% dualled
  • End of 2035: 100% dualled

A9 dualling milestones showing 50% by 2030, 67% by 2032, 91% by 2034 and 100% by 2035

Read in order, these figures show the programme reaching its halfway point five years before completion. Progress then speeds up. Roughly a sixth more of the route follows in the next two years. A further quarter comes in the two years after that, and the final stretch in 2035.

The last stage of the plan is also the steepest. This is one reason the later milestones carry more delivery risk than the earlier ones.

In January 2026, the Government confirmed how the remaining work on the A9 dualling project timeline would be delivered. It will use capital-funded design and build or similar contracts. These will be procured under a Framework Agreement covering five contracts.

The programme is estimated to cost £3.97 billion at April 2025 prices. Transport Scotland notes that this falls within the original 2008 estimate once inflation is taken into account.

Sections Already Open and Under Way

Two sections of the route already operate as dual carriageway:

  • Kincraig to Dalraddy
  • Luncarty to Pass of Birnam

Transport Scotland’s programme pages also list the status and expected opening dates for other named sections. These include Tomatin to Moy, Tay Crossing to Ballinluig and Pitlochry to Killiecrankie. The remaining future sections sit within the 2026 Delivery Plan. Some sections are in construction now. The rest fall under the procurement framework described below.

A9 route map from Perth to Inverness showing open sections and sections named on the programme pages

There is one honest caveat on section-level detail. The evidence behind this article does not give a complete, verifiable opening date for every remaining section in one place. This matters most for the later sections.

To find the expected opening date of a specific stretch near you, check the programme pages linked above. A summary could fill the gap with assumption. The programme pages are also the most reliable source for the latest A9 roadworks and traffic management updates between Perth and Inverness.

How the Remaining Work Is Funded

Funding matters because it decides whether the rest of the programme can be let as contracts at all.

The 2026 Delivery Plan confirms that the remaining sections will use capital funding. This money comes from the Scottish Government’s own capital budget rather than any alternative financing route. The work will be let as design and build or similar contracts. Under this model, one contractor takes responsibility for both the detailed design and the construction of a section.

These contracts are being let through a single Framework Agreement. It covers five procurement contracts for the remaining projects. A framework of this kind sets the terms and the pool of suppliers once. Individual projects can then be awarded under it without starting a fresh procurement each time.

Transport Scotland indicated in January 2026 that procurement under this arrangement would begin in spring 2026. The framework is valued at £1.94 billion. It covers the final five projects on the Perth to Inverness corridor.

The Latest Procurement Update

The most recent official update on the framework is dated 14 September 2026.

In that procurement update, Transport Scotland said it had formally invited tenders for the £1.94 billion A9 Dualling Delivery Framework Agreement. The framework covers the remaining sections between Perth and Inverness. Inviting tenders marked the final stage of that procurement process. The agreement was expected to conclude by the end of 2026 and would then be used to procure the final five projects.

Transport Scotland described this as “keeping the A9 Dualling programme on track for completion by the end of 2035”.

Two points are worth separating here. The invitation to tender and the expected end-2026 conclusion are concrete procurement milestones. The phrase “on track” is Transport Scotland’s own view of its programme. No independent third party has made that assessment.

Procurement moving to schedule is a necessary step towards the 2035 target. On its own, it does not confirm the target will be met.

Why 2035 Is Not Guaranteed

No source used here confirms that the A9 will be fully dualled by the end of 2035. The evidence shows that this is Transport Scotland’s official target. It is also the basis on which the programme is currently planned, funded and procured.

Several points support treating 2035 as a plan rather than a fixed outcome.

It has moved before. The 2011 commitment gave a 2025 completion date. The 2023 plan moved this to the end of 2035. This is a documented precedent for the timetable changing.

Most of the work is not yet contracted. As of the September 2026 update, the framework for the final five projects was still in procurement. Its conclusion was expected by the end of that year. Construction dates for sections not yet awarded cannot be treated as fixed.

Several delivery stages still carry scheduling risk. Each remaining section depends on procurement, contract award, statutory processes and then construction itself. Any of these stages can affect timing.

No one has measured the risk. The published material sets out no contingency scenarios. It puts no likelihood of further delay either. There is no evidence-based way to say how probable it is that 2035 will hold.

Some older articles still give 2025 as the completion date. The current official target is 2035. The 2025 date is a superseded commitment. The change was made in December 2023, as described earlier.

How to Follow Official Updates

Procurement stages, contract awards and section opening dates can all change. Anyone who needs current information should go to the source rather than rely on secondary summaries.

Transport Scotland publishes ongoing updates through its A9 dualling programme pages. You can register there for programme news and alerts covering traffic management and project progress. This is the most direct way to hear about schedule changes as they are announced. It also covers any changes that affect a particular section.

Frequently Asked Questions

What is the official completion date for the A9 dualling programme?

The end of 2035. The Scottish Government set this date in its Delivery Plan, and Transport Scotland reaffirmed it in January 2026. It is the official target and planning basis, not a guaranteed delivery date.

Has the A9 dualling completion date changed before?

Scottish Ministers committed in December 2011 to dualling the route by 2025. The December 2023 Delivery Plan replaced that commitment and set completion at the end of 2035.

How will the remaining sections of the A9 be funded and contracted?

The work will use capital funding and design and build or similar contracts. These are procured under a single Framework Agreement covering five contracts. As of 14 September 2026, Transport Scotland had invited tenders for that £1.94 billion framework. The procurement was expected to conclude by the end of 2026.

How can I get the latest official updates on A9 dualling progress?

Register for news and alerts on Transport Scotland’s A9 dualling programme pages. They carry programme updates and traffic management information directly from the delivering authority.

The Short Version

The A9 between Perth and Inverness is officially planned to be fully dualled by the end of 2035. The work will happen in stages. Half the route should be dualled by the end of 2030, 67% by the end of 2032 and 91% by the end of 2034. Two sections are already open. The final five projects are still going through a framework procurement that Transport Scotland expected to conclude by the end of 2026.

The 2035 date is a Government commitment with a history of change behind it. Nothing in the published material independently confirms it will be met. For anything beyond the checkpoints set out here, watch Transport Scotland’s own programme updates and alerts.

Planning a move along the A9 corridor? Browse our latest houses to buy in Inverness and across the Highlands.

Share
Hamish Homes logo
Written by
Alexa Murray
Company Director
Decorative section divider

More Stories

October 28, 2026

WHAT DOES IT ACTUALLY COST TO LIVE OFF GRID AROUND INVERNESS?

Generic off-grid articles usually give you a broad range, then leave out the parts that matter most around Inverness: heating, winter resilience, water, access, and local compliance. The honest answer...
October 21, 2026

WHAT IS CROFTING AND DOES IT STILL HAPPEN TODAY?

Yes — crofting still happens today in Scotland. In plain terms, crofting is a uniquely Scottish system of land tenure linked to small-scale rural landholding and land use, particularly in the Highland...
October 12, 2026

SELLING IN THE HIGHLANDS? WHY NOW COULD BE THE RIGHT TIME TO PLAN

Changing costs for second-home owners could affect the number of properties coming to market. Homeowners considering a sale may benefit from understanding their position sooner. From 1 April 2026, Hig...
October 6, 2026

WHAT DOES THE HEAT IN BUILDINGS BILL MEAN FOR OLDER HOMES?

If you own an older home, you may have seen headlines that make it sound as if you will soon be forced into expensive heating upgrades. The reality is more nuanced than that. There is a clear policy d...
September 24, 2026

WHY ARE EPC RATINGS BECOMING SUCH A BIG DEAL IN THE HIGHLANDS?

EPC ratings are becoming a more important part of property discussions in the Highlands. For some homes, particularly rural and off-gas-grid properties, heating choices, energy costs and the practical...

Sign In to Our Newsletter

Subscribe to Our Newsletter! Stay updated with the latest properties and exclusive offers from us. Sign in now to receive fresh, new information directly to your inbox. Don't miss out on your dream property—join our community today